Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 48
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
completed Final Technical Report is
resubmitted on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed completed
Final Technical Report is submitted
on 23th September 2013
16 Seblat – Ipuh
Link No.010.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th March 2014
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui – Biha
Social Issues:
The Larap report of Package no.04 Krui – Biha Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report had been submitted to the
World Bank by PMU dated 10 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the Package no.01 Krui – Biha dated 25 Nov 2013.
Environmental Issues:
A SPPL has already been sent to the Bank by PMU dated 30 September 2013 and t
he CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on construction stage
will be done by the contractors.
Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 49
6.6.2 Package No.02: Padang Sawah – Simpang Empat
Social Issues:
The Larap report of Package no.02 Padang Sawah – Simpang Empat West Sumatera Province has already approved by the World Bank dated 13 January 2013, and the
monitoring report has been submitted to the World Bank by PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by
DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank by
PMU dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The project Sumatera the remaining of 21 affected people did not receive compensation from
Local Government yet. Now CTC is waiting a proof of the compensation payment for 21 affected people from local government. Contract signing for the Package no.02 Padang
Sawah - Sp.Empat dated 6 Dec 2013.
Environmental Issues:
Official Letter from Director of Implementation Affairs Region I has been issued to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding to the
request of the SPPL submission. Then on 27 December 2013 SPPL document already sent to Director of Implementation Affairs Region I by Official Letter from Kepala Balai Besar
Pelaksanaan Jalan Nasional II. The SPPL document has been submitted to the World Bank on 20 January 2014.
The CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on
construction stage will be done by the contractors.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
The Larap report of Package no.03 Manggopoh - Padang Sawah West Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report
has been submitted to the World Bank by PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people did not receive compensation from Local
Government yet. CTC has received proof of the compensation payment for 5 from 15 affected people from local government. A monitoring report has submitted to the World
Bank dated 28 February 2014.
Contract signing for the Package no.03 Manggopoh – Padang Sawah dated 6 Dec 2013.