Monitoring Report of the LARAP Package No. 6
11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. b Head of Satker in Bengkulu informed PMU thru letter that LARAP implementation regarding land acquisition will be completed by the end of August 2014 C. Update during this reporting month of August 2014 a LARAP is under implementation by the Local Government.12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the documents for revision in line with CTC s comments • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. B. Pending Issues, Concern and Actions a Revised LARAP document still to be submitted to World Bank for NOLParts
» WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Current Implementation Situation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Disbursement WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Visit Procurement WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Project Development WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Project Objective WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Scope of Services CTC Consultants
» CTC Contract CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Procurements WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 5.98 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 13.85 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 7.01 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» - 14.36 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam
» Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
» Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20 : Lubuk Alung - Sicincin
» Monitoring Report of the LARAP Package No. 21 : Lubuk Alung - Kurataji
» Anti Corruption Action Plan ACAP
» Community Representative Observers CRO
» Publication Disclosure Anti Corruption Issues
» Road Safety Audit WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» General Overview Management Information System
» Database Management Information System
» World Bank Missions World Bank and GOI Compliance
» Design and Supervision Consultant DSC
» Road Sector Institutional Development
» Updating the Project Management Manual PMM
» Annual Training Program TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Progress TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Activities Plan for next month September 2014
» Complaint Handling System CHS
» Activities During This Month August 2014
» Package No.01: Krui Biha Social Issues: Package No.02: Padang Sawah Simpang Empat
» Package No.03: Manggopoh Padang Sawah Package No.04: Ipuh Bantal
» Package No.05: Sp. Rampa Poriaha Package No.06: Psr.Pedati Kerkap
» Package No.07: Indrapura Tapan
» Package No.10: Sp. Empat Air Balam Social Issues: Package No.11: Bantal - Mukomuko Social Issues:
» Package No.16: Sebelat Ipuh Social Issues:
» Package No.19: Lais - Bintunan Social Issues: Package No.20: Lubuk Alung Sicincin Social Issues:
» Synchronizing Data of The FMIS Application 1 Background
» Draw Downs and Future Costs Disbursement Quality Assurance
» Project Risks and Mitigation Measures