Package No.03: Manggopoh Padang Sawah Package No.04: Ipuh Bantal

Monthly Progress Report August 2014 Western I ndonesia National Roads I mprovement Project 58

6.6.12 Package No12: Kambang Indrapura Social Issues:

 LARAP documents are under final review by CTC prior to submission to World Bank for NOL Environmental Issues:  CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design.  No Objection Letter NOL for EIA AMDAL was issued by World Bank on August 8, 2014.

6.6.13 Package No.13: Sp. Rukis Tj. Kemuning Social Issues:

 Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.14 Package No.14: Painan Kambang Social Issues:

 Corrected LARAP documents still to be submitted to World Bank for NOL. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.  No Objection Letter NOL for EIA AMDAL was issued by World Bank on August 8, 2014.

6.6.15 Package No.15: Sibolga Bts. Tapsel Social Issues:

 LARAP implementation Monitoring Report from SatkerPPK still to be submitted to PMUCTC for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.16 Package No.16: Sebelat Ipuh Social Issues:

 Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.  LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents to need be prepared.