Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 57
issues which will be integrated in to the design. World Bank issued No Objection Letter NOL on August 8, 2014 for the AMDAL documents that
were prepared by Subdit TLKJAMDAL local consultant hired by BALAI.
6.6.8 Package No.08: Bts Kota Pariaman Manggopoh
Social Issues: No Objection Letter NOL was issued on August 12, 2014 by World Bank on the LARAP.
LARAP is under implementation process by the Local Government. Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.9 Package No.09: Rantau Tijang Kota Agung
Social Issues: Still no issues and concerns.
Environmental Issues: CTC need to check the recommendations of UKLUPL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.10 Package No.10: Sp. Empat Air Balam Social Issues:
No Objection Letter NOL was issued on August 12, 2014 on the LARAP documents. LARAP is under implementation process by the Local Government.
Environmental Issues: CTC need to check the recommendations of AMDAL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.11 Package No.11: Bantal - Mukomuko Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for
review and for submission to World Bank.
Environmental Issues: CTC need to check the recommendations of AMDAL in the field for clearance of environmental
issues which will be integrated in to the design.
Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 58
6.6.12 Package No12: Kambang Indrapura Social Issues:
LARAP documents are under final review by CTC prior to submission to World Bank for NOL Environmental Issues:
CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental
issues which integrated in to the design. No Objection Letter NOL for EIA AMDAL was issued by World Bank on August 8, 2014.
6.6.13 Package No.13: Sp. Rukis Tj. Kemuning Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for
review and for submission to World Bank.
Environmental Issues: CTC need to check the recommendations of UKLUPL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.14 Package No.14: Painan Kambang Social Issues:
Corrected LARAP documents still to be submitted to World Bank for NOL.
Environmental Issues: CTC need to check the recommendations of AMDAL in the field for clearance of environmental
issues which will be integrated in to the design. No Objection Letter NOL for EIA AMDAL was issued by World Bank on August 8, 2014.
6.6.15 Package No.15: Sibolga Bts. Tapsel Social Issues:
LARAP implementation Monitoring Report from SatkerPPK still to be submitted to PMUCTC for
review and for submission to World Bank.
Environmental Issues: CTC need to check the recommendations of UKLUPL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.16 Package No.16: Sebelat Ipuh Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for
review and for submission to World Bank. LARAP documents for this Package No.16 covers only land acquisition for the road link. If there
are land acquisition for the bridge site, a separate LARAP documents to need be prepared.