Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 55
Group Pack No. Name of Sub-project
Technical Design Review Road Safety Audit Road Safety
Audit Report by BINTEK
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
18 Mukomuko
Bts.Sumbar Link No.015.3
By DSC By DSC
By DSC -
- -
19 Lais - Bintuan
Link No.009.1 completed
completed completed completed -
Final Technical Report is submitted on 17th September 2013
20 Lubuk Alung Sicincin Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
21 Lubuk Alung Kuraitaji Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui Biha Social Issues:
Existing mosque is partially traversed due widening of the existing travelledway. Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed,
where the road alignment centerline will be shifted to the other side. Land acquisition is required on the other side of the road centerline alignment if the new action
plan push through.
Environmental Issues: CTC have reviewed and gave comments on RKPPL that was submitted by the Contractor.
Contractor still to resubmitted the revised RKPPL. CTC to check if the DSC and Contractor implement the requirements and recommendations in the
AMDAL on the site and incorporated in the design. CTC is waiting for the submission of AMDAL drawings recommendations from DSCContractors.
6.6.2 Package No.02: Padang Sawah Simpang Empat
Social Issues: Remaining twenty one 21 affected persons are not yet compensated by the Local Government.
Five 5 of the twenty one 21 affected persons are residing along the proposed bridge site of Air Gadang Bridge. Twenty four 24 new affected persons included in the new LARAP are not yet
completed by the Local Government.
CTC completed the review of the RKPPL and sent back to Contractor thru email. Monitoring Report concerning the payments to the remaining affected peoples still to be
prepared for submission to World Bank.
Environmental Issues: CTC completed the review of the RKPPL and sent back to Contract for finalization.
CTC need to check the recommendation UKLUPL bridge in the field for clearance of
environmental issues which have to be integrated in to the design.
Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 56
6.6.3 Package No.03: Manggopoh Padang Sawah
Social Issues: Documents for compensation payments for the remaining three 3 affected persons processed
and resolve by the Local Government. Monitoring Report concerning compensation payments to the three 3 remaining affected
persons still to be prepared for submission to World Bank.
Environmental Issues: CTC completed the review of the RKPPL and sent back to Contractor thru email for finalization.
6.6.4 Package No.04: Ipuh Bantal
Social Issues: No more issue and concern
Environmental Issues: CTC to assist the BALAI locally hired consultant to decide the sampling locations and
environmental mitigation of project. The locally hired consultant have already conducted sampling and conducted presentation of UKLUPL in PJN BALAI III in Bengkulu on August 27,
2014. UKL and UPL reports are under preparation by the Consultant for submission.
6.6.5 Package No.05: Sp. Rampa Poriaha
Social Issues: PMUCTC is awaiting the LARAP implementation Report
Environmental Issues: CTC need to check the recommendations of UKLUPL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.6 Package No.06: Psr.Pedati Kerkap
Social Issues: Monitoring Reports of the LARAP s implementation have to be prepared and submitted for
review and for submission to World Bank.
Environmental Issues: CTC need to check the recommendations of UKLUPL in the field for clearance of environmental
issues which will be integrated in to the design.
6.6.7 Package No.07: Indrapura Tapan
Social Issues: Corrected LARAP documents on-going final review by CTC prior to submission to World Bank.
Environmental Issues: CTC need to check the recommendation of AMDAL in the field for clearance of environmental