Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 54
6.5 Road Safety Audit
6.5.1 Activities During This Month August 2014
There are three 3 activities during this month, i.e: 1. Site visit to Seblat Ipuh Package No. 16 for Road Safety Audit at Detailed Engineering Design
Stage on August 13th 15th, 2014. 2. Preparation of Seblat Ipuh Package No. 16 Road Safety Audit Report,
3. Checking of Final Engineering Design of Bts. Kota Pariaman Manggopoh Package 8 and Sp. Empat Sp. Air Balam Package 10 for Road Safety according to TLKJ Recommendations at the
Road Safety Audit Report Detailed Engineering Design Stage.
6.5.2 Current status of the project for technical field as of August 2014. The Details of Progress of Technical Design Review and Road Safety Audit as of the end of August 2014
is as shown in the tabulated format and included as Appendix B.
Technical Design Review Road Safety Audit Report Status
Group Pack No. Name of Sub-project
Technical Design Review Road Safety Audit Road Safety
Audit Report by BINTEK
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa Poriaha
Link No.015.xx completed
completed completed completed -
Final Technical Report is resubmitted
on 17th September 2013 6
PS.Pedati - Kerkap Link No.010.0
completed completed completed completed
- Final Technical Report is submitted
on 17th September 2013 7
Indrapura Tapan Link No.019.0
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS
aFinal Technical Advisory is submitted on 5th February 2013
bFinal RSA Report is submitted on May 2014
8 Bts.Pariaman
Manggopoh Link No.024.0
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS
aFinal Technical Advisory is submitted on 5th February 2013
bFinal RSA Report is submitted on May 2014
9 Rantau Tijang Kota
Agung Link No.026.1
By DSC By DSC
By DSC -
- -
10 Sp.Empat Sp. Air
Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS
aFinal Technical Advisory is submitted on 5th February 2013
b Final RSA Report is submitted on May 2014
11 Bantal - Mukomuko Link No.015.2
completed completed completed completed
- Final Technical Report is
resubmitted on 16th August 2013
12 Kambang Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS
aFinal Technical Advisory is submitted on 5th February 2013
bFinal RSA Report is submitted on May 2014
13 SP.Rukis - TJ.Kemuning Link No.006.0
completed completed completed completed
- Final Technical Report is
resubmitted on 16th August 2013
AWP -3
14 Painan Kambang
Link No.017.1 By DSC
By DSC By DSC
Technical Advisory
- Final Technical Advisory is submitted
on 28 May 2014 15 Sibolga Bts TapSel
Link No.016.1 completed
completed completed completed -
Final Technical Report is submitted on 23th September 2013
16 Seblat Ipuh
Link No.010.0 -
Completed -
Completed -
Completed Technical
Advisory -
Final Technical Advisory is submitted on 27th March 2014
17 Sp.Gng Kemala
Pg.Tampak Link No.061.1
PPC-TA WINRIP PPC-TA
WINRIP PPC-TA
WINRIP -
- -
Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 55
Group Pack No. Name of Sub-project
Technical Design Review Road Safety Audit Road Safety
Audit Report by BINTEK
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
18 Mukomuko
Bts.Sumbar Link No.015.3
By DSC By DSC
By DSC -
- -
19 Lais - Bintuan
Link No.009.1 completed
completed completed completed -
Final Technical Report is submitted on 17th September 2013
20 Lubuk Alung Sicincin Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
21 Lubuk Alung Kuraitaji Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui Biha Social Issues:
Existing mosque is partially traversed due widening of the existing travelledway. Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed,
where the road alignment centerline will be shifted to the other side. Land acquisition is required on the other side of the road centerline alignment if the new action
plan push through.
Environmental Issues: CTC have reviewed and gave comments on RKPPL that was submitted by the Contractor.
Contractor still to resubmitted the revised RKPPL. CTC to check if the DSC and Contractor implement the requirements and recommendations in the
AMDAL on the site and incorporated in the design. CTC is waiting for the submission of AMDAL drawings recommendations from DSCContractors.
6.6.2 Package No.02: Padang Sawah Simpang Empat
Social Issues: Remaining twenty one 21 affected persons are not yet compensated by the Local Government.
Five 5 of the twenty one 21 affected persons are residing along the proposed bridge site of Air Gadang Bridge. Twenty four 24 new affected persons included in the new LARAP are not yet
completed by the Local Government.
CTC completed the review of the RKPPL and sent back to Contractor thru email. Monitoring Report concerning the payments to the remaining affected peoples still to be
prepared for submission to World Bank.
Environmental Issues: CTC completed the review of the RKPPL and sent back to Contract for finalization.
CTC need to check the recommendation UKLUPL bridge in the field for clearance of
environmental issues which have to be integrated in to the design.