Technical Assistance for Capacity Building for Disaster Risks Reduction
4.2 Procurements
Procurement shall be conducted under the Bank s Procurement Procedures as mentioned in the Loan Agreement. The International Competitive Bidding ICB based on the Bank letter Ref. WINRIP136 will apply to the packages with the construction estimated cost more than US 25 Million to comply with the new Bank s threshold for ICB. According to the GOI regulation, a prequalification shall be applied for the packages with the construction estimated cost more than IDR 10 Billion. Review from previous procurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojects qualification still used Pre-Qualification and for remaining sub-project must be process with Post Qualification. As well as for all NCB the World Bank also requested to follow Post Qualification in procurement process. All subprojects for WP-1 have been started with prequalification since 30 December 2011 for ICB multiple contract. This was an advanced procurement action agreed by both DGH and the World Bank prior to the CTC establishment. All AWP-1 sub-projects had signed the contract. The last 2 sub-projects, Package 02: Pd. Sawah Simpang Empat and Package 03: Manggopoh Padang Sawah, signed the contract on December 6, 2013 and NOL for disbursement for all 4 packages had been issued by the World Bank on December 10, 2013. As of the reporting month August 2014, bids for Package No. 17 Sp. Gunung Kemala-Pugung Tampak were opened on August 15, 2014. Currently, Bid Evaluation Report BER is under preparation and evaluation by the Procurement Committee POKJA. It is expected that the Report will be finalized on orParts
» WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Current Implementation Situation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Disbursement WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Visit Procurement WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Project Development WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Project Objective WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Scope of Services CTC Consultants
» CTC Contract CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Procurements WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 5.98 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 13.85 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» 7.01 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» - 14.36 WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam
» Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
» Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20 : Lubuk Alung - Sicincin
» Monitoring Report of the LARAP Package No. 21 : Lubuk Alung - Kurataji
» Anti Corruption Action Plan ACAP
» Community Representative Observers CRO
» Publication Disclosure Anti Corruption Issues
» Road Safety Audit WINRIP DOC MPR CTC MPR No.20 2014 08 2014 08 11 00224.
» General Overview Management Information System
» Database Management Information System
» World Bank Missions World Bank and GOI Compliance
» Design and Supervision Consultant DSC
» Road Sector Institutional Development
» Updating the Project Management Manual PMM
» Annual Training Program TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Progress TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Activities Plan for next month September 2014
» Complaint Handling System CHS
» Activities During This Month August 2014
» Package No.01: Krui Biha Social Issues: Package No.02: Padang Sawah Simpang Empat
» Package No.03: Manggopoh Padang Sawah Package No.04: Ipuh Bantal
» Package No.05: Sp. Rampa Poriaha Package No.06: Psr.Pedati Kerkap
» Package No.07: Indrapura Tapan
» Package No.10: Sp. Empat Air Balam Social Issues: Package No.11: Bantal - Mukomuko Social Issues:
» Package No.16: Sebelat Ipuh Social Issues:
» Package No.19: Lais - Bintunan Social Issues: Package No.20: Lubuk Alung Sicincin Social Issues:
» Synchronizing Data of The FMIS Application 1 Background
» Draw Downs and Future Costs Disbursement Quality Assurance
» Project Risks and Mitigation Measures
Show more