Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 30
C. Update during this reporting month of August 2014 a LARAP documents is submitted to the World Bank on August 7, 2014.
b World Bank approved LARAP documents on August 12, 2014. c LARAP is under implementation process by the Local Government.
11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
Province : Bengkulu
A. Previous Status : •
September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. •
After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL.
• Bank conducted their review and their comments were relayed to PMU thru letter on
November 20, 2013. •
On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by
incorporating their comments. •
PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.
• World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP
documents for implementation. B. Pending Issues, Concern and Actions
a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
b Head of Satker in Bengkulu informed PMU thru letter that LARAP implementation regarding land acquisition will be completed by the end of August 2014
C. Update during this reporting month of August 2014 a LARAP is under implementation by the Local Government.
12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
Province : Sumatera Barat
A. Previous Status : •
CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 •
CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the
documents for revision in line with CTC s comments •
Revised LARAP documents from P2JN Consultant resubmitted in June 2014. •
CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. B. Pending Issues, Concern and Actions
a Revised LARAP document still to be submitted to World Bank for NOL
Monthly Progress Report August 2014
Western I ndonesia National Roads I mprovement Project 31
C. Update during this reporting month of August 2014 a LARAP documents is on-going final review prior to submission to World Bank.
13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis Tj. Kemuning
Province : Bengkulu
A. Previous Status : •
September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. •
After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL.
• Bank conducted their review and their comments were relayed to PMU thru letter on
November 20, 2013. •
On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by
incorporating their comments. •
PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.
• World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP
documents for implementation. B. Pending Issues, Concern and Actions
a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
b Head of Satker in Bengkulu informed PMU thru letter that LARAP implementation regarding land acquisition will be completed by the end of August 2014
C. Update during this reporting month of August 2014 a No update this month.
14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang
Province : Sumatera Barat
A. Previous Status : •
CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014. •
After CTC s review of the documents, comments were transmitted in the form of a MEMO DINAS to Balai II thru the Directorate of Implementation in Region I.
• Revised LARAP documents from P2JN Consultant resubmitted in June 2014.
B. Pending Issues, Concern and Actions a Revised LARAP documents still to be submitted to World Bank for NOL.
C. Update during this reporting month of August 2014 a No update during this period