Project Risks and Mitigation Measures

Monthly Progress Report August 2014 Western I ndonesia National Roads I mprovement Project 73 7 ISSUES and RECOMMENDATIONS

7.1 Current Situation

The main issues during this month of August 2014 are as follows: a The slow progress of procurement proceedings b Provisions for additional funds to cover claims for contract escalations and expected variation orders c The finalization of the Project Management Manual PMM and Quality Assurance Manual QAM d The considerable negative slippage behind schedule of two 2 on-going construction sub-projects

7.2 Action Required

a The main cause of the delay in procurement is attributed to the flow of communication between POKJA, PMU, CTC and the World Bank in finalizing the procurement documents. To minimize or totally eliminate the delays in securing Bank s concurrence and issuance of No Objection Letter NOL, special meeting shall be held regularly among all concerned to discuss each comments and suggestions which are to be incorporated in any documents prior to formally submitting to the Bank. b As the budgets for the price escalation and expected variation orders were not included in the original cost estimates, PMU shall discuss this matter with the higher authorities to request fund allocation to cover the additional cost. c As there are now four 4 on-going civil works contract packages under construction and sooner another four 4 will be on tender, the Project Management Manual PMM and the Quality Assurance Manual QAM shall be formally approved. In the absence of an officially approved Quality Assurance Manual, a Draft Final version of the manual was issued to the Design Supervision Consultant DSC for their provisional reference in the quality requirement of the on-going sub-project. d Two 2 of the four 4 on-going construction packages were on an alarming stage due to considerable negative slippages. To be on schedule or reduce the negative slippage to a manageable level, Design Supervision Consultant DSC shall initiate and schedule a high level meeting to be attended by no other than the Contractor s principal and other concerned authorities. Contractors shall be required to submit realistic action plans and catch-up schedule to be implemented, if possible, on a two 2 shifts per day work schedule. 8 CORRESPONDENCES During the period the CTC received and issued letters. Lists of letters received and issued are shown in Appendix J. Western I ndonesia National Roads I mprovement Project ANNEXES Annex P-1 : Package No. 1 Annex P-2 : Package No. 2 Annex P-3 : Package No. 3 Annex P-4 : Package No. 4 MONTH : Package No. Time Elapsed Days 229 Name Time Elapsed 35,78 Project Manager Scheduled Progress 31,58 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress 5,98 Supervision Consultant Balance -25,60 Commencement Date Progress This Month 1,19 Take Over Date Time for Complation Days 640 Addendum-1 t tus d t Contract Amount Rp. umul tiv p 6 Contract Amount Add-1 + PPN Include advance payment Comp um tu l um um Tot l st this to this h to this Month Month Month Month I G e n e r a l 5 5 6 II D r a i n a g e 9 5 65 III Earthworks 95 84 0,41 1,25 2,72 IV Pavement Widening Shoulders 1,47 - - - - V Granular Pavement 9,22 0,53 0,41 0,94 7,09 VI Asphalt Pavement 40,14 - - - 3,82 VII S t r u c t u r e s 1,09 0,57 0,20 0,77 0,86 VIII Reinstatement Minor Works 1,20 0,09 0,03 0,12 0,15 IX Day Work 0,14 - - - 0,05 X Routine Maintenance Works 0,36 0,18 0,01 0,19 0,20 TOTAL 100,00 4,79 1,20 5,99 31,58 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 0,22 0,87 1,69 5,62 11,11 18,06 24,50 31,58 38,99 46,36 53,25 60,68 67,46 74,81 80,69 83,98 87,62 91,27 93,71 96,16 98,75 100,00 0,10 0,58 0,79 1,59 2,93 3,71 4,79 5,98 0,12 0,29 0,90 4,03 8,18 14,35 19,71 25,60 Scheduled Progress Original Actual Progress Balance Div Description PHYSICAL PROGRESS MONITORING TABLE 2014 2015 Year Month The month of time for complation - Late of Field Engineering Decision - DSC and Contractor to discuss with PPK regarding the finalization of the Field Engineering. PHYSICAL WORK PROGRESS BY CATEGORY 134.909.211.000,00 DISBURSEMENT 14.106.688.650,00 03-Jul-14 - The Contractor has not started works as per the - The contractor have to started the main work approved schedule such as drainage works RENARDET S.A JV - Insufficient manpower, equipment and financial - The contractor have to add manpower aspecialy SUPARJONO, ST,MT AM OU NT 08-Jan-14 resources to undertake the needed acceleration for drainage work 09-Okt-15 of works. EXECUTIVE SUMMARY REPORT Agust- 14 PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS 01 TI M E August 25, 2014 BIHA - KRUI MAJOR PROBLEMS ACTION TO BE TAKEN 10 20 30 40 50 60 70 80 90 100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PH YS IC AL PR OG RE S THE MONTH OF TIME FOR COMPLATION PROGRESS SCHEDULE PACKAGE 01 Schedule Actual EXECUTIVE SUMMARY REPORT edit 9 Sep 2014_8EF690.xlsx ExSum P-1