Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko

Monthly Progress Report August 2014 Western I ndonesia National Roads I mprovement Project 32

15. Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • CTC received the Draft Final LARAP documents on September 30,2013 from Balai. • PMU submitted the documents to World Bank on October 28, 2013 requesting further review and acceptance. • On October 28, 2013, World Bank returned to PMU the documents with comments to be considered in finalizing the documents for resubmission. • On October 31, 2013, PMU requested the Director of Implementation Affairs thru SatkerPPK to address the World Bank comments • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Light of Ways and removal of obstruction. • PPKSatker and the Local Government started the preparation stage of land acquisition B. Pending Issues, Concern and Actions a LARAP implementation under preparation stage by SATKERPPK. C. Update during this reporting month of August 2014 a No update this month.

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30,2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. b LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared.