Activities During This Month August 2014

Monthly Progress Report August 2014 Western I ndonesia National Roads I mprovement Project 56

6.6.3 Package No.03: Manggopoh Padang Sawah

Social Issues:  Documents for compensation payments for the remaining three 3 affected persons processed and resolve by the Local Government.  Monitoring Report concerning compensation payments to the three 3 remaining affected persons still to be prepared for submission to World Bank. Environmental Issues:  CTC completed the review of the RKPPL and sent back to Contractor thru email for finalization.

6.6.4 Package No.04: Ipuh Bantal

Social Issues:  No more issue and concern Environmental Issues:  CTC to assist the BALAI locally hired consultant to decide the sampling locations and environmental mitigation of project. The locally hired consultant have already conducted sampling and conducted presentation of UKLUPL in PJN BALAI III in Bengkulu on August 27, 2014. UKL and UPL reports are under preparation by the Consultant for submission.

6.6.5 Package No.05: Sp. Rampa Poriaha

Social Issues:  PMUCTC is awaiting the LARAP implementation Report Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.6 Package No.06: Psr.Pedati Kerkap

Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.7 Package No.07: Indrapura Tapan

Social Issues:  Corrected LARAP documents on-going final review by CTC prior to submission to World Bank. Environmental Issues:  CTC need to check the recommendation of AMDAL in the field for clearance of environmental Monthly Progress Report August 2014 Western I ndonesia National Roads I mprovement Project 57 issues which will be integrated in to the design.  World Bank issued No Objection Letter NOL on August 8, 2014 for the AMDAL documents that were prepared by Subdit TLKJAMDAL local consultant hired by BALAI.

6.6.8 Package No.08: Bts Kota Pariaman Manggopoh

Social Issues:  No Objection Letter NOL was issued on August 12, 2014 by World Bank on the LARAP.  LARAP is under implementation process by the Local Government. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.9 Package No.09: Rantau Tijang Kota Agung

Social Issues:  Still no issues and concerns. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.10 Package No.10: Sp. Empat Air Balam Social Issues:

 No Objection Letter NOL was issued on August 12, 2014 on the LARAP documents.  LARAP is under implementation process by the Local Government. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.11 Package No.11: Bantal - Mukomuko Social Issues:

 Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.