Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 54
prepared for submission to World Bank.
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
CTC need to check the recommendation UKLUPL bridge in the field for clearance of environmental issues which have to be integrated in to the design.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
Documents for compensation payments for the ten 10 remaining affected persons being processed by the Local Government.
Monitoring Report concerning compensation payments to the ten 10 remaining affected persons still to be prepared for submission to World Bank.
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
6.6.4 Package No.04: Ipuh – Bantal
Social Issues:
No more issue and concern
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
CTC to assist the BALAI locally hired consultant to decide the sampling locations and environmental mitigation of project.
6.6.5 Package No.05: Sp. Rampa – Poriaha
Social Issues:
PMUCTC is awaiting the LARAP implementation Report
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.6 Package No.06: Psr.Pedati – Kerkap
Social Issues:
Monitoring Reports of the LARAP’s implementation have to be prepared and submitted
Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 55
for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.7 Package No.07: Indrapura – Tapan
Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank.
Environmental Issues:
CTC need to check the recommendation of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
CTC is waiting AMDAL documents from the Subdit TLKJAMDAL local consultant hired by BALAI for submission to the Bank.
6.6.8 Package No.08: Bts Kota Pariaman – Manggopoh
Social Issues:
To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant
CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as
soon as possible
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.9 Package No.09: Rantau Tijang – Kota Agung
Social Issues:
Still no issues and concerns.
Environmental Issues:
CTC need to check the recommendations of UKLUPL is the field for clearance of environmental issues which will be integrated in to the design.
6.6.10 Package No.10: Sp. Empat – Air Balam Social Issues:
To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant.