Activities During This Month May 2014 Current status of the project for technical field as of 31 May 2014.

Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 54 prepared for submission to World Bank. Environmental Issues:  CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.  CTC need to check the recommendation UKLUPL bridge in the field for clearance of environmental issues which have to be integrated in to the design.

6.6.3 Package No.03: Manggopoh – Padang Sawah

Social Issues:  Documents for compensation payments for the ten 10 remaining affected persons being processed by the Local Government.  Monitoring Report concerning compensation payments to the ten 10 remaining affected persons still to be prepared for submission to World Bank. Environmental Issues:  CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.

6.6.4 Package No.04: Ipuh – Bantal

Social Issues:  No more issue and concern Environmental Issues:  CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.  CTC to assist the BALAI locally hired consultant to decide the sampling locations and environmental mitigation of project.

6.6.5 Package No.05: Sp. Rampa – Poriaha

Social Issues:  PMUCTC is awaiting the LARAP implementation Report Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.6 Package No.06: Psr.Pedati – Kerkap

Social Issues:  Monitoring Reports of the LARAP’s implementation have to be prepared and submitted Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 55 for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.7 Package No.07: Indrapura – Tapan

Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank. Environmental Issues:  CTC need to check the recommendation of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.  CTC is waiting AMDAL documents from the Subdit TLKJAMDAL local consultant hired by BALAI for submission to the Bank.

6.6.8 Package No.08: Bts Kota Pariaman – Manggopoh

Social Issues:  To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant  CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.9 Package No.09: Rantau Tijang – Kota Agung

Social Issues:  Still no issues and concerns. Environmental Issues:  CTC need to check the recommendations of UKLUPL is the field for clearance of environmental issues which will be integrated in to the design.

6.6.10 Package No.10: Sp. Empat – Air Balam Social Issues:

 To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant.