Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 53
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
completed Final Technical Report is
resubmitted on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 By DSC By DSC By DSC
Technical Advisory
Final Technical Advisory is submitted on 28 May 2014
15 Sibolga – Bts TapSel
Link No.016.1 completed completed completed
completed Final Technical Report is
submitted on 23th September
2013 16
Seblat – Ipuh Link No.010.0
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 27th March 2014 17
Sp.Gng Kemala–Pg.Tampak Link No.061.1
PPC-TA WINRIP
PPC-TA WINRIP
PPC-TA WINRIP
- -
18 Mukomuko – Bts.Sumbar
Link No.015.3 By DSC By DSC By DSC
- -
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 By DSC By DSC By DSC
Technical Advisory
Final Technical Advisory is submitted on 23 May 2014
21 Lubuk Alung – Kuraitaji
Link No.009.1 By DSC By DSC By DSC
Technical Advisory
Final Technical Advisory is submitted on 23 May 2014
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui – Biha
Social Issues:
Existing mosque is partially traversed due widening of the existing travelledway. Due to resistance to partially demolished and rebuild the mosque, a new action plan is
proposed, where the road alignment centerline will be shifted to the other side. Land acquisition is required on the other side of the road centerline alignment if the new
action plan push through.
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
CTC to check if the DSC and Contractor mplement the requirements and recommendations in the AMDAL on the site and incorporated in the design.
6.6.2 Package No.02: Padang Sawah – Simpang Empat
Social Issues:
Remaining twenty one 21 affected persons are not yet compensated by the Local Government. Five 5 of the twenty one 21 affected persons are residing along the
proposed bridge site of Air Gadang Bridge. Documents for compensation payments are being processed by the Local Government.
Monitoring Report concerning the payments to the remaining affected peoples still to be
Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 54
prepared for submission to World Bank.
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
CTC need to check the recommendation UKLUPL bridge in the field for clearance of environmental issues which have to be integrated in to the design.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
Documents for compensation payments for the ten 10 remaining affected persons being processed by the Local Government.
Monitoring Report concerning compensation payments to the ten 10 remaining affected persons still to be prepared for submission to World Bank.
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
6.6.4 Package No.04: Ipuh – Bantal
Social Issues:
No more issue and concern
Environmental Issues:
CTC need to carried out training of RKPPL for DSC and Contractor staff cause of no environmental specialist in DSC Team.
CTC to assist the BALAI locally hired consultant to decide the sampling locations and environmental mitigation of project.
6.6.5 Package No.05: Sp. Rampa – Poriaha
Social Issues:
PMUCTC is awaiting the LARAP implementation Report
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.6 Package No.06: Psr.Pedati – Kerkap
Social Issues:
Monitoring Reports of the LARAP’s implementation have to be prepared and submitted