Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 56
CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as
soon as possible.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.11 Package No.11: Bantal - Mukomuko Social Issues:
Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.12 Package No12: Kambang – Indrapura Social Issues:
To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant
CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as
soon as possible
Environmental Issues:
CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design.
CTC is waiting AMDAL Doc from the Subdit TLKJ AMDAL Consultant.
6.6.13 Package No.13: Sp. Rukis – Tj. Kemuning Social Issues:
Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.14 Package No.14: Painan – Kambang Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank
Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 57
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
CTC is waiting AMDAL Documents from the Subdit TLKJ AMDAL Consultant
6.6.15 Package No.15: Sibolga – Bts. Tapsel Social Issues:
LARAP implementation report from SatkerPPK still to be submitted to PMUCTC for review.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.16 Package No.16: Sebelat – Ipuh Social Issues:
Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank.
LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents to need be
prepared.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.17 Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:
LARAP implementation report is not yet submitted to PMUCTC.
Environmental Issues:
CTC need to check the recommendations of AMDAL UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.18 Package No.18: Mukomuko – Bts. Sumbar Social Issues:
Still no issues and concerns
Environmental Issues: