Package No.05: Sp. Rampa – Poriaha Package No.06: Psr.Pedati – Kerkap

Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 56  CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.11 Package No.11: Bantal - Mukomuko Social Issues:

 Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.12 Package No12: Kambang – Indrapura Social Issues:

 To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant  CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible Environmental Issues:  CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design.  CTC is waiting AMDAL Doc from the Subdit TLKJ AMDAL Consultant.

6.6.13 Package No.13: Sp. Rukis – Tj. Kemuning Social Issues:

 Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.14 Package No.14: Painan – Kambang Social Issues:

 Corrected LARAP documents still to be submitted for final review prior to submission to World Bank Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 57 Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.  CTC is waiting AMDAL Documents from the Subdit TLKJ AMDAL Consultant

6.6.15 Package No.15: Sibolga – Bts. Tapsel Social Issues:

 LARAP implementation report from SatkerPPK still to be submitted to PMUCTC for review. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.16 Package No.16: Sebelat – Ipuh Social Issues:

 Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank.  LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents to need be prepared. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.17 Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:

 LARAP implementation report is not yet submitted to PMUCTC. Environmental Issues:  CTC need to check the recommendations of AMDAL UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.18 Package No.18: Mukomuko – Bts. Sumbar Social Issues:

 Still no issues and concerns Environmental Issues: