Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 26
B. Pending Issues, Concern and Actions a LARAP’s implementation still to be implemented by SATKER.
C. Update during this reporting month of May 2014 a Just before the end of this reporting month, on May 30, 2014, the World Bank
interpose No Objection to the revised LARAP documents for implementation.
7. Monitoring Report of the LARAP Package No. 7 : Indrapura - Tapan
Province
: Sumatera Barat
A. Previous Status : •
CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014
• After CTC’s review of the documents, comments were transmitted in the form of a
MEMO DINAS to Balai II thru the Directorate of Implementation in Region I. B. Pending Issues, Concern and Actions
a Corrected LARAP documents still to be submitted for final review prior to submission to World Bank.
C. Update during this reporting month of May 2014 a Finalization of corrected LARAP documents is under preparation by CTC
8. Monitoring Report of the LARAP Package No. 8 : Bts. Pariaman - Manggopoh
Province
: Sumatera Barat
A. Previous Status : •
CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013
• CTC reviewed the documents with comments transmitted to PMU on September 9,
2013 and PMU forwarded to P2JNLocal Consultants the CTC’s comments requesting the documents for revision in line with CTC’s comments
B. Pending Issues, Concern and Actions a To date May 2014 the revised LARAP documents have not yet been
resubmitted by P2JN Local Consultant b CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to
issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible
C. Update during this reporting month of May 2014 a Finalization of LARAP documents by CTC
Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 27
9. Monitoring Report of the LARAP Package No. 9 : Rantau Tijang – Kota Agung
Province
: Lampung
A. Previous Status : •
LARAP documents are still to be prepared. B. Pending Issues, Concern and Actions
a Still no issues and concerns. C. Update during this reporting month of May 2014
a Nothing to report this period.
10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat – Sp. Air Balam
Province
: Sumatera Barat
A. Previous Status : •
CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013
• CTC reviewed the documents with comments transmitted to PMU on September 9,
2013 and PMU forwarded to P2JNLocal Consultants the CTC’s comments requesting the documents for revision in line with CTC’s comments
B. Pending Issues, Concern and Actions a To date May 2014 the revised LARAP documents have not yet been
resubmitted by P2JN Local Consultant b CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to
issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible
C. Update during this reporting month of May 2014 a Finalization of LARAP documents by CTC
11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
Province
: Bengkulu
A. Previous Status : •
September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang.
• After CTC’s review, PMU forwarded the documents to World Bank on November 13,
2013 requesting for No Objection Letter NOL. •
Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013.
• On November 27, 2013, the World Bank sent letter to the Director of Planning to
request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments.
• PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP