Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 23
4.6.2.2 Social Issues 1. Monitoring Report of the LARAP
Package No. 1 : Krui – Biha Province
: Lampung
A. Previous Status : •
LARAP documents approved by World Bank on January 4, 2013 •
Monitoring Report approved by World Bank on April 18, 2013 B. Pending Issues, Concern and Actions
a Existing mosque is partially traversed due widening of the existing travelled way.
b Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed, where the road alignment centerline will be shifted to
the other side. c Land acquisition is required on the other side of the road centerline alignment
if the new action plan push through. C. Update during this reporting month of May 2014
a On-going construction b No Update this period
2. Monitoring Report of the LARAP Package No. 2 : Padang Sawah – Sp. Empat
Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on January 13, 2013 •
Monitoring Report approved by World Bank on July 19, 2013 B. Pending Issues, Concern and Actions
a Remaining twenty one 21 affected persons are not yet compensated by the Local Government. Five 5 of the twenty one 21 affected persons are
residing along the proposed bridge site of Air Gadang Bridge. b Documents for compensation payments are being processed by the Local
Government. c Monitoring Report concerning the payments to the remaining affected persons
still to be prepared for submission to World Bank. C. Update during this reporting month of May 2014
a On-going construction b In line with the latest “Aide Memoire” April 28-May 19, 2014 a simple LARAP
documents is under preparation to be implemented on additional land acquisition specifically, on roadway cut section where a wider road right of
ways are required to attain the desireddesigned cut slope ratio of 1:1.
Monthly Progress Report May 2014
Western I ndonesia National Roads I mprovement Project 24
3. Monitoring Report of the LARAP Package No. 3 : Manggopoh – Padang Sawah
Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on January 4, 2013 •
Monitoring Report approved by World Bank on April 18, 2013 •
CTC received proof of compensation payments for five 5 of the affected persons out of the remaining fifteen 15 persons and Monitoring Report was submitted to
World Bank on February 28, 2014.
B. Pending Issues, Concerns and Actions a Documents for compensation payments for the ten 10 remaining affected
persons being processed by the Local Government. b Monitoring Report concerning compensation payments to the ten 10
remaining affected persons still to be prepared for submission to World Bank. C. Update during this reporting month of May 2014
a On-going construction b Processing of documents for the 10 remaining affected persons were withheld
by the Local Government as these 10 persons could not be located in their addresses shown in the LARAP.
c Local Government has paid 67 new additional Project Affected Persons for compensation of additional road right of ways for roadway cut sections to
attain the required cut slope of 1:1. d Monitoring Report for the additional land acquisition is under preparation by
CTC for submission to World Bank by next month.
4. Monitoring Report of the LARAP Package No. 4 : Ipuh – Bantal
Province
: Bengkulu
A. Previous Status : •
LARAP documents approved by World Bank on December 10, 2012 •
CTC received proof of payments for 157 affected persons out of the 227 Project Affected Persons.
• Monitoring Report was submitted by PMU to World Bank on December 24, 2013
• World Bank transmitted their comments on the Monitoring Report to PMU on
January 6, 2014. •
For the remaining 70 affected persons, Local Government settled their compensation payments in January 2014 and February 2014.
• Monitoring Report for the compensation of the remaining 70 affected persons was
submitted by PMU to the World Bank on February 28, 2014. •
World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report.
B. Pending Issues, Concern and Actions a No more pending issues and concerns.