Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 21

4.6 Environmental and Social Considerations

4.6.1 Current Overall Situation

A project category is assigned to each package as either Category A, B or C depending on the likely degree of influence on environmental issues with a brief explanation as follows : Category A project is one which will have a significant negative impact on the environment and may have an influence on areas outside the actual project area. A project classified as such requires an AMDAL ANDAL, RKLRPL study. Category B project is one which affects the people or the environment to some extent but with a smaller impact than a Category A. The required environmental analysis is a UKLUPL study only. Category C project has minimal effect on the people or environment and an environmental analysis is not required. SPPL or Standard operational procedures SOP or SKPPL are used to handle any minor problem which may arise. Details of packages that require environmental and social safeguard are given in Appendix E and the following table provides a summary of the work involved in the 21 WINRIP packages. All the 21 packages require environmental impact investigation. All 39 studies 18 environmental studies need approval by Environmental Agency BLH. And 21 social studies SLARAP and LARAP require the approval of the World Bank. Up to the end of May 2014 17of 18 packages 90 has received BLH approval then the current have 12 of 21social studies or 57 has received approval from the World Bank. Works Program No of Packages No of Investigations Approval by Remarks BLH World Bank AWP-1 4 8 AMDAL x 1 UKLUPL x 2 SPPL x 4 Full LARAP x 4 1 AMDAL 1 UKLUPL 4 SPPL 4 Full LARAP Approved – NOL issued by WB LARAP and AMDAL paket 117, except for SPPL AWP-2 8 17 AMDAL Study x 4 UKLUPL x 4 Simple LARAP x 1 Full LARAP x 8 4 UKLUPL 4 AMDAL 1 SLARAP 1 one Study AMDAL for threes packages, are Packages No.7, 12 and 14 packages on AWP2 AWP3. 1 one Study AMDAL for two packages, are Packages No.11 16. packages on AWP2 AWP3. AWP-3 9 14 Full LARAPx 8 AMDAL Study x AMDAL OK = paket No.1 17 AWP1 2 Full LARAP Approved – NOL issued by WB include AMDAL except for