Monitoring Report of the LARAP Package No. 8 : Bts. Pariaman - Manggopoh

Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 28 documents and was resubmitted again on May 21, 2014 due to some minor corrections. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank. C. Update during this reporting month of May 2014 a Just before the end of this reporting month, on May 30, 2014, the World Bank interpose No Objection to the revised LARAP documents for implementation.

12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC’s comments requesting the documents for revision in line with CTC’s comments B. Pending Issues, Concern and Actions a To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant b CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible C. Update during this reporting month of May 2014 a Finalization of LARAP documents by CTC

13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis – Tj. Kemuning

Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC’s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 29 B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank. C. Update during this reporting month of May 2014 a Just before the end of this reporting month, on May 30, 2014, the World Bank interpose No Objection to the revised LARAP documents for implementation.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014 • After CTC’s review of the documents, comments were transmitted in the form of a MEMO DINAS to Balai II thru the Directorate of Implementation in Region I. B. Pending Issues, Concern and Actions a Corrected LARAP documents still to be submitted for final review prior to submission to World Bank. C. Update during this reporting month of May 2014 a No update during this period

15. Monitoring Report of the LARAP Package No. 15 : Sibolga – Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • CTC received the Draft Final LARAP documents on September 30,2013 from Balai. • PMU submitted the documents to World Bank on October 28, 2013 requesting further review and acceptance. • On October 28, 2013, World Bank returned to PMU the documents with comments to be considered in finalizing the documents for resubmission. • On October 31, 2013, PMU requested the Director of Implementation Affairs thru SatkerPPK to address the World Bank comments • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Light of Ways and removal of obstruction. • PPKSatker and the Local Government started the preparation stage of land acquisition B. Pending Issues, Concern and Actions a LARAP implementation under preparation stage by SATKERPPK. C. Update during this reporting month of May 2014 a No update this month