Monitoring Report of the LARAP Package No. 5 : Sp. Rampa – Poriaha Monitoring Report of the LARAP Package No. 6 : Pasar Pedati - Kerkap

Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 27

9. Monitoring Report of the LARAP Package No. 9 : Rantau Tijang – Kota Agung

Province : Lampung A. Previous Status : • LARAP documents are still to be prepared. B. Pending Issues, Concern and Actions a Still no issues and concerns. C. Update during this reporting month of May 2014 a Nothing to report this period.

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat – Sp. Air Balam

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC’s comments requesting the documents for revision in line with CTC’s comments B. Pending Issues, Concern and Actions a To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant b CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible C. Update during this reporting month of May 2014 a Finalization of LARAP documents by CTC

11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko

Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC’s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 28 documents and was resubmitted again on May 21, 2014 due to some minor corrections. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP’s implementation have to be prepared and submitted for review and for submission to World Bank. C. Update during this reporting month of May 2014 a Just before the end of this reporting month, on May 30, 2014, the World Bank interpose No Objection to the revised LARAP documents for implementation.

12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC’s comments requesting the documents for revision in line with CTC’s comments B. Pending Issues, Concern and Actions a To date May 2014 the revised LARAP documents have not yet been resubmitted by P2JN Local Consultant b CTC to suggest to PMUDirectorate of Implementation Affairs Region 1 to issue follow-up letter to P2JNLocal Consultant requesting that the documents must be resubmitted as soon as possible C. Update during this reporting month of May 2014 a Finalization of LARAP documents by CTC

13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis – Tj. Kemuning

Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC’s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.