Monitoring of Environmental Aspects During Construction

Monthly Progress Report May 2014 Western I ndonesia National Roads I mprovement Project 24

3. Monitoring Report of the LARAP Package No. 3 : Manggopoh – Padang Sawah

Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on January 4, 2013 • Monitoring Report approved by World Bank on April 18, 2013 • CTC received proof of compensation payments for five 5 of the affected persons out of the remaining fifteen 15 persons and Monitoring Report was submitted to World Bank on February 28, 2014. B. Pending Issues, Concerns and Actions a Documents for compensation payments for the ten 10 remaining affected persons being processed by the Local Government. b Monitoring Report concerning compensation payments to the ten 10 remaining affected persons still to be prepared for submission to World Bank. C. Update during this reporting month of May 2014 a On-going construction b Processing of documents for the 10 remaining affected persons were withheld by the Local Government as these 10 persons could not be located in their addresses shown in the LARAP. c Local Government has paid 67 new additional Project Affected Persons for compensation of additional road right of ways for roadway cut sections to attain the required cut slope of 1:1. d Monitoring Report for the additional land acquisition is under preparation by CTC for submission to World Bank by next month.

4. Monitoring Report of the LARAP Package No. 4 : Ipuh – Bantal

Province : Bengkulu A. Previous Status : • LARAP documents approved by World Bank on December 10, 2012 • CTC received proof of payments for 157 affected persons out of the 227 Project Affected Persons. • Monitoring Report was submitted by PMU to World Bank on December 24, 2013 • World Bank transmitted their comments on the Monitoring Report to PMU on January 6, 2014. • For the remaining 70 affected persons, Local Government settled their compensation payments in January 2014 and February 2014. • Monitoring Report for the compensation of the remaining 70 affected persons was submitted by PMU to the World Bank on February 28, 2014. • World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report. B. Pending Issues, Concern and Actions a No more pending issues and concerns.